Responding to schedule changes in build‐to‐order supply chains
Реагирование на изменения графика в цепочках поставок с производством под заказ
2004-12-08
SCID: 54.1/fekmf7ey
Discuss with AI
build-to-order supply chainsform postponementschedule changessupplier reaction strategiessupply contracts
Figures from the paper
Abstract (AI)
Abstract This multiple case study explores the reaction strategies suppliers use to respond to short‐term dynamics of schedule changes in build‐to‐order supply chains. We examine the relationship and supply chain processes between a notebook computer manufacturer and five component suppliers. Two distinct reaction strategies emerge from these five buyer–supplier dyads. The “reduce uncertainty” strategy emphasizes supply contracts with a high degree of restrictiveness, relatively infrequent schedule revisions, and a high level of form postponement. The “cope with uncertainty” strategy emphasizes flexible supply contracts, relatively frequent schedule revisions, and low levels of form postponement. Eight propositions are formulated to understand the linkage between a supplier's power, its short‐term process flexibility, and the elements of its reaction strategy. The paper concludes by proposing future research directions.
Key Findings
1
A multiple case study of a notebook manufacturer and five component suppliers identifies two distinct strategies for handling short-term schedule changes.
2
Eight propositions link supplier power and short-term process flexibility to the elements of suppliers’ reaction strategies.
3
The “cope with uncertainty” strategy combines flexible supply contracts, frequent schedule revisions, and limited form postponement.
4
The “reduce uncertainty” strategy combines restrictive supply contracts, infrequent schedule revisions, and extensive form postponement.
Research Object
supplier reaction strategies in build-to-order supply chains, particularly the buyer–supplier relationships and supply chain processes between a notebook computer manufacturer and component suppliers
Research Subject
how suppliers respond to short-term schedule changes through uncertainty-reduction versus uncertainty-coping strategies, including contract restrictiveness or flexibility, schedule revision frequency, form postponement, supplier power, and short-term process flexibility