Supply Chain Management for Prefabricated Building Projects in Hong Kong
Управление цепями поставок в проектах строительства сборных зданий в Гонконге
2020-01-09
SCID: 54.1/h8d3y2kk
Discuss with AI
automated data collectionprecast componentsprefabricated building projectsreal-time informationsupply chain management
Figures from the paper
Abstract (AI)
Prefabricated building projects (PBPs) have gained worldwide popularity over the past few decades because of their various benefits. Supply chain management (SCM) is critical to the successful delivery of PBPs because supply chains are complex, involving multiple processes and stakeholders. Poor SCM in PBPs causes cost overruns and schedule delays. This study investigates production, transportation, and assembly in a PBP in Hong Kong to quantitatively analyze and critique its SCM. Automated data collection technologies were adopted to obtain real-time information on precast components throughout the supply chain. Findings from the study show that limited consideration of resource planning, significant assembly delay, overproduction, excess inventory, and long lead times are severe problems. The root causes of these problems include poor supply chain planning, poor communication between stakeholders, and poor workflow control. This study objectively reveals the true picture of SCM for PBPs using real-time information on an entire supply chain. The results provide an in-depth understanding of SCM in PBPs, which will be of great value to stakeholders in improving PBP supply chain performance.
Key Findings
1
Automated data collection technologies provide real-time information on precast components, enabling objective assessment of supply chain performance.
2
Severe supply chain problems include inadequate resource planning, significant assembly delays, overproduction, excess inventory, and long lead times.
3
The findings provide stakeholders with detailed evidence for improving supply chain management and performance in prefabricated building projects.
4
The identified root causes are poor supply chain planning, weak stakeholder communication, and inadequate workflow control.
5
The study quantitatively evaluates production, transportation, and assembly processes across an entire prefabricated building project supply chain in Hong Kong.
Research Object
the supply chain of a prefabricated building project in Hong Kong, including production, transportation, and assembly of precast components
Research Subject
supply chain management performance, problems, and root causes, including planning, coordination, workflow control, delays, overproduction, inventory, and lead times